Logo
File #: 8317-16    Version: 1
Type: Briefing/Report (Dept,BCC) - Action Requested Status: Business
File created: 8/18/2016 In control: County Council - Regular Session
On agenda: 8/30/2016 Final action:
Title: Approval of Amendment No. 2 to the Laramie River Station Participation Power Sales Agreement between the City of Lincoln and the County of Los Alamos
Presenters: Steve Cummins
Indexes (Council Goals): 2016 Council Goal – Quality Governance – Operational Excellence – Manage Commercial Growth Well Following an Updated, Concise, and Consistent Comprehensive Plan
Attachments: 1. A - Laramie River Station Participation Power Sales Agreement Amendment No 2, 2. B - Laramie River Station Participation Power Sales Agreement Dated June 25th 1987, 3. C - Proposed Exhibit A To Laramie River Station Participation Power Sales Agreement (Monthly Power Costs)
Related files: 8316-16
Title
Approval of Amendment No. 2 to the Laramie River Station Participation Power Sales Agreement between the City of Lincoln and the County of Los Alamos
Recommended Action
I move that Council approve Amendment No.2 to the Laramie River Station Participation Power Sales Agreement
Utilities Manager's Recommendation
The Utilities Manager recommends that Council approve the agreement as requested.
Board, Commission or Committee Recommendation
The Board of Public Utilities recommends that Council approve the agreement as requested.
Body
In 1987 the County signed a Participation Power Sales Agreement with the City of Lincoln for 0.61% share (10 Mega Watts) of the Laramie River Station generating capacity. The original debt service for Los Alamos County’s share of Laramie River Station will retire on August 31, 2016. The current contract with the City of Lincoln, doing business as Lincoln Electric System (LES), is somewhat unclear on how to handle cost after the repayment of the initial debt service. This amendment will clarify billing practices associated with retirement of the major debt service for Laramie River Station. This amendment will replace the current Exhibit A (Monthly Power Cost) in its entirety, and no other changes will be made to the general terms of the contract.
Alternatives
Do nothing and Section 1 of the current Exhibit A will become zero and all remaining cost will be billed through sections 2, 3, 4, and 5 of Exhibit A.
Fiscal and Staff Impact/Planned Item
No fiscal or staff impact associated with this contract amendment. With the payoff of the original debt service, this resource will see an approximate 30% reduction in cost. Similar to the San Juan Generating Station, LRS is also facing huge capital investments in new environmental controls over the next couple of years. DPU believe this resource will still be economical for many years to come.