Title: Recommendation of AGR24-04c Task Order No.16 with Dub-L-EE in the Total Amount of $460,000.00, Including a 15% Contingency and NMGRT for the Tank 4A 18-inch Transmission Waterline Repair in Two Mile Canyon; and Recommendation of Budget Revision No. 2027-23
Presenters: James Martinez
Indexes (Council Goals): Quality Excellence - Effective, Efficient, and Reliable Services, Quality Governance - Fiscal Stewardship, DPU FY26 - 1.0 Provide Safe and Reliable Utility Services, DPU FY26 - 2.0 Achieve and Maintain Excellence in Financial Performance
Attachments: 1. A - AGR24-04c Task Order No. 16, 2. B - Tank 4A Transmission Line Repair Plan Set, 3. C - Dub-L-EE Quote, 4. D - Budget Revision 2027-23
Title

Recommendation of AGR24-04c Task Order No.16 with Dub-L-EE in the Total Amount of $460,000.00, Including a 15% Contingency and NMGRT for the Tank 4A 18-inch Transmission Waterline Repair in Two Mile Canyon; and Recommendation of Budget Revision No. 2027-23

Recommended Action

I move that the Board of Public Utilities recommend AGR24-04c Task Order No.16 with Dub-L-EE in the total amount of $399,841.72, plus 15% Contingency, and NMGRT having a total budget of $460,000 for the Tank 4A 18-inch Transmission Waterline Repair in Two Mile Canyon and forward to Council for approval.

I further move that the Board recommend Budget Revision 2027-23 in the amount of $460,000.00 and forward to Council for approval.

Utilities Manager's Recommendation

The Utilities Manager recommends that the Board approve the motion as presented.

Body

This project will repair a blowout in the existing 18-inch concrete cylinder pipe (CCP) transmission line in the Two Mile Canyon on LANL property. Dub-L-EE will remove the affected pipe and concrete encasement, install approximately 60 feet of 18-inch ductile iron pipe along the existing alignment, reconnect to the existing CCP, and provide new concrete encasement. Work also includes canyon access, designated equipment staging, storm water and access-road protection, testing, and restoration to support reliable water service to LANL facilities.

LANL permit delays and additional requirements required changing contractors from Parker Construction, whose contract expired to Dub-L-EE. The bottom of the canyon is severely eroded requiring a new concrete encased pipe crossing. The proposed total is $459,839.26 that is now a pipe replacement and concrete encasement versus a lining project scoped under Parker. This is an increase of $225,012.59 over the previous Parker Construction task order total of $234,826.67 including contingency and NMGRT. 

Alternatives

If the Board and Council do not award the project, sta...