Logo
File #: RE0505-22a    Version: 1
Type: Resolution Status: Public Hearing
File created: 8/8/2022 In control: Board of Public Utilities
On agenda: 8/17/2022 Final action: 8/17/2022
Title: Approval of Resolution 22-16 Authorization to Apply To Water Trust Board 2023 Cycle
Presenters: James Alarid
Indexes (Council Goals): DPU FY25 - 1.0 Provide Safe and Reliable Utility Services, DPU FY25 - 2.0 Achieve and Maintain Excellence in Financial Performance
Attachments: 1. A - Resoulution No. 22-16, 2. B - Debt Service Evaluation Including WTB Award
Related files: RE0505-22

Title

Approval of Resolution 22-16 Authorization to Apply To Water Trust Board 2023 Cycle

 

Recommended Action

I move that the Board of Public Utilities Approve Resolution 22-16 Authorizing Submission of an Application to the Water Trust Board for the 2023 Funding Cycle, and forward to Council for approval.

 

Utilities Manager's Recommendation

The Utilities Manager recommends that the Board approve as presented.

 

Body

The Department of Public Utilities (DPU) has chosen to apply to the New Mexico Finance Authority, Water Trust Board (WTB) in the 2023 cycle to fund the State Road 4 Water Transmission Line Replacement project.  The project is estimated to cost $6 million.  We plan to apply for $5 million from the WTB.  We do not know the amount that will be awarded, but if successful we anticipate the award will have a 60% grant component, 40% loan component (20-year term @ 0.25% interest rate), and a required match of 20% of the awarded amount which would come from DPU water production capital funds.

 

The project is driven by the NMDOT's plans to reconstruct NM-4 between White Rock and the NM-502/NM-4 intersection in 2024.  The existing 16" water transmission line is located along NM-4 roadway and has been experiencing leaks more frequently in recent years.  The pipeline is concrete cylinder material which is difficult to repair and failures are extremely destructive.  The new road will be widened placing a large amount of the pipeline beneath the new asphalt.  The pipeline must remain in its current alignment as it must stay within an existing 25' easement.  DPU had planned this waterline replacement project in near the future but will move it up to coordinate with the road construction to avoid the risk of damages if the line fails beneath the new road and the complexities of replacing the line after the road is widened.  The DPU will partner with the NMDOT and construct the waterline as part of the road reconstruction project.

 

Alternatives

The resolution is a mandatory portion of the application submittal.  If the resolution is not approved an application will not be submitted.

 

Fiscal and Staff Impact

In 2022 the DPU was awarded a $400,000 grant from the state legislature for the project. 

 

The WTB is the only grant funding available of for the project.  Due to the NMDOT project, DPU is moving the project up to 2024, which also requires we complete the project in its entirety in 2024.  This eliminates options such as phasing the project or building additional capital to fund the project.  If the WTB funding is not awarded, or only a portion is awarded, the DPU will proceed with the existing plan to fund the project with a Drinking Water State Revolving Loan.  We have provided a debt profile as Attachment B  which includes the new $2 million loan that is the 40% component of the project, assuming we receive the WTB award in 2023.  Our debt service coverage ratio stays above 1.2, the value NMFA & NMED consider the lower limit when considering loan applications. 

 

Attachments

A - Resolution 22-16

B - Debt Service Evaluation Including WTB Award