Legislation Details

File #: 21666-26a    Version: 1
Type: Construction Contract Status: Consent
File created: 5/8/2026 In control: Board of Public Utilities
On agenda: 5/19/2026 Final action:
Title: Award of Bid No. 26-61 for the Tank Piping Upgrades Phase 2 Project to NM Underground Utilities, Inc. in the Amount of $607,890.00 plus Applicable NMGRT
Presenters: James Martinez
Indexes (Council Goals): Quality Excellence - Effective, Efficient, and Reliable Services, DPU FY26 - 1.0 Provide Safe and Reliable Utility Services
Attachments: 1. A - IFB 26-61 Construction Plans

Title

Award of Bid No. 26-61 for the Tank Piping Upgrades Phase 2 Project to NM Underground Utilities, Inc. in the Amount of $607,890.00 plus Applicable NMGRT

Recommended Action

I move that the Board of Public Utilities recommend the award of Bid No. 26-61 for the Tank Piping Upgrades Phase 2 Project with the base bid amount of $528,600.00 plus a 15% contingency in the amount of $79,290.00, for a total project amount of $607,890.00, plus applicable NM gross receipts tax to NM Underground Utilities, Inc. and forward to County Council for approval.

Utilities Manager's Recommendation

The Utilities Manager recommends that the Board approve the motion as presented.

Body

The Twin Tank Piping Upgrades Phase 2 Project was advertised on April 5, 2026. Following the bid opening on May 5, 2026, four bids were received, ranging from $528,600.00 to $774,727.00. The two lowest bids were within 2% of the engineer’s estimate, and NM Underground Utilities, Inc. was identified as the lowest responsive bidder.

 

The control valves for Twin Tank, a 7.8-million-gallon water storage tank in Western area, are dilapidated and difficult to operate and maintain. This project will replace these valves and create a bypass for the building that houses them. It will also update a control valve inside the S-site booster station, add a flow meter, and create a bypass for Tank 4A, among other miscellaneous improvements to the County’s water production infrastructure. This will reduce the O&M resources required for operation, improve DPU staff safety, and lessen failure risk.

Alternatives

If the Board does not award the project, staff will continue to allocate staff and monetary resources to pipeline and valve maintenance and pursue less desirable means to keep the system operational. 

Fiscal and Staff Impact/Planned Item

The project has been budgeted through Water Production in FY 2026 in the amount of $900,000.00.

Attachments

A - IFB 26-61 Construction Plans