Title: Award of Bid No. IFB 26-25 for the Purpose of the Piedra Loop Underground Replacement Project with Bixby Electric in the Amount of $1,182,877.44, plus Applicable GRT for a Term of 4.5 Months
Presenters: Dennis Astley
Attachments: 1. A - Construction Plans

Title

Award of Bid No. IFB 26-25 for the Purpose of the Piedra Loop Underground Replacement Project with Bixby Electric in the Amount of $1,182,877.44, plus Applicable GRT for a Term of 4.5 Months

Recommended Action

I move that the Board of Public Utilities recommend the Award of Bid No. IFB 26-26 for the Purpose of the Piedra Loop Underground Replacement Project with Bixby Electric in the Amount of $985,731.20, and a 20% contingency in the amount of $197,146.24 , for a total of $1,182,877.44, plus Applicable Gross Receipts Tax and forward to Council for approval.

Utilities Manager's Recommendation

The Utilities Manager recommends that the Board approve the motion as presented.

Body

Bids were solicited for replacement of approximately one mile of direct buried underground primary cable along Piedra Loop. This project will extend the cable to connect it to the next phase of the cable replacement project and complete a loop feed from two directions.  Five bids were received at the bid opening on April 2 with the lowest qualified bid being from Bixby Electric.

Alternatives

Not awarding the bid, however, DPU has had reliability issues in this neighborhood.  Not replacing the primary electric circuit will increase the risk of a lengthy cable outage in the area.

Fiscal and Staff Impact/Planned Item

FY 2026 Budget has $550,000 for Piedra Loop and the balance of capital funds will be redirected from FY 2025 La Senda and Valle del Sol project in the amount of $718,000.  No planned staff impact to implement this project, however Electric Distribution still has two engineering/project manager vacancies to fill.

Attachments