File #: 20077-25    Version: 1
Type: Briefing/Report (Dept,BCC) - Action Requested Status: Consent
File created: 11/14/2025 In control: County Council - Regular Session
On agenda: 12/16/2025 Final action:
Title: Approval of Modification 25 to Extend the Contract Term by Ninety-Days of the Electric Coordination Agreement (ECA) between the Incorporated County of Los Alamos and the United States Department of Energy (DOE)
Presenters: Ben Olbrich
Indexes (Council Goals): Quality Excellence - Effective, Efficient, and Reliable Services, Quality Governance - Intergovernmental and Regional Relations, DPU FY26 - 1.0 Provide Safe and Reliable Utility Services, DPU FY26 - 6.0 Develop and Strengthen Partnerships
Attachments: 1. A - ECA MOD 25
Related files: 20077-25a
Title
Approval of Modification 25 to Extend the Contract Term by Ninety-Days of the Electric Coordination Agreement (ECA) between the Incorporated County of Los Alamos and the United States Department of Energy (DOE)
Recommended Action
I move that Council approve Modification 25 to Extend the Contract Term by Ninety-Days of the Electric Coordination Agreement (ECA) between the Incorporated County of Los Alamos and the Department of Energy (DOE).
Utilities Manager's Recommendation
The Utilities Manager recommends that the Council approve the motion as presented.
BPU's Recommendation
BPU met on December 10, 2025 and recommends that Council to approve Modification 25.
Body
The Power Pool was established through the Electric Coordination Agreement (ECA) between Los Alamos County and The Department of Energy in 1985. (Note: In 2002 the National Nuclear Security Administration was established as a branch of the Department of Energy and took over responsibility for the ECA. The acronyms NNSA, DOE, and LANL may be used interchangeably throughout this discussion). Through the contract, both parties contribute the power from, and costs of, each of the respective "Pool Approved Resources" into the pool, and those costs are then allocated back to the parties pro rata according to each party's usage. The contract has been renewed continuously since 1985. Historically the County has contributed approximately 75% of the resources, while the Lab has accounted for approximately 80% of the load.

The proposed Modification (MOD) 25 adds ninety (90) days to the current agreement's expiration date of December 31,2025. If approved, then the new expiration date will be March 31, 2026. This extension will allow time for DOE to complete their contracting process to present back to the County.

The Los Alamos Power Pool met on December 2, 2025, and approved this MOD 25.
Alternatives
The Council could elect not to accept the proposed MOD 25, and the current agreement would...

Click here for full text