Title: Award of Bid No. 26-18 in the Amount of $6,109,481.60 plus Applicable Gross Receipts Tax to TLC Plumbing & Utility for Construction of Denver Steels Phase II Improvements Project; Establish a Project Budget in the Amount of $7,573,640.00 for Roadway and Utility Work; and Approve Related Budget Revision 2026-06 for Utilities in the Amount of $573,640.00
Presenters: Eric Ulibarri; Eric Martinez
Attachments: 1. A – Board of Public Utilities Agenda Documents, August 20, 2026, 2. B - Project Area Map, 3. C - Project Budget Spreadsheet, 4. D - Budget Revision Form 2026-06 (Utilities)
Title
Award of Bid No. 26-18 in the Amount of $6,109,481.60 plus Applicable Gross Receipts Tax to TLC Plumbing & Utility for Construction of Denver Steels Phase II Improvements Project; Establish a Project Budget in the Amount of $7,573,640.00 for Roadway and Utility Work; and Approve Related Budget Revision 2026-06 for Utilities in the Amount of $573,640.00
Recommended Motion
I move that Council Award of Bid No. 26-18 in the amount of $6,109,481.60 plus applicable Gross Receipts Tax to TLC Plumbing & Utility for construction of Denver Steels Phase II Improvements Project; Establish a Project Budget in the amount of $7,573,640.00 for Roadway and Utility Work; and Approve related Budget Revision 2026-06 for utilities in the amount of $573,640.00
Board, Commission or Committee Recommendation
On August 20, 2025 the Board of Public Utilities (BPU) approved the Utilities portion of the bid. BPU recommends forwarding the project to Council for approval. A copy of the Board’s agenda documentation is attached for reference (Attachment A).
County Manager's Recommendation
The County Manager recommends that Council approve the motion as presented.
Body
A public meeting was held on April 3, 2025 in conjunction with the regular Transportation Board meeting to present the project and acquire input.
On July 17, 2025 the County advertised a formal competitive solicitation for project construction through Invitation for Bids No. 26-18, One (1) response was received on August 7, 2025 and the evaluation committee recommends awarding the bid to TLC Plumbing & Utility.
Roadway work will include full reconstruction of the following streets: 36th Street between Orange Street and Ridgeway Drive, Pueblo Drive between 36th and 35th Street, Questa Drive between 36th and 35th Street, and Ridgeway Drive between 36th and 35th Street. The scope of work includes removal of existing asphalt surface and base course and replacement of new base course and new 4-inch of asphalt surface, c...