Title: Approval of Task Order No. 35, Agreement No. AGR22-18a for Otowi 2 and S-site Booster Station Renovations with Riteccon Construction, Inc. in the amount of $338,619.65 and a contingency of $100,000.00, plus Applicable Gross Receipts Tax, for the Purpose of the LAC Booster Stations Rehabilitation
Presenters: James Martinez
Indexes (Council Goals): Quality Excellence - Effective, Efficient, and Reliable Services, Quality Excellence - Infrastructure Asset Management, DPU FY26 - 1.0 Provide Safe and Reliable Utility Services
Attachments: 1. A - AGR 22-18a Task Order No 35, 2. B - Ritecon Construction, Inc. Price Agreement

Title

Approval of Task Order No. 35, Agreement No. AGR22-18a for Otowi 2 and S-site Booster Station Renovations with Riteccon Construction, Inc. in the amount of $338,619.65 and a contingency of $100,000.00, plus Applicable Gross Receipts Tax, for the Purpose of the LAC Booster Stations Rehabilitation

Recommended Action

I move that the Board of Public Utilities approve Task Order No. 35, Agreement No. AGR  22-18a for Otowi 2 and S-site Booster Station Renovations with Ritecon Construction, Inc. in the amount of $338,619.65 and a contingency of $100,000.00, plus applicable gross receipts tax, for the purpose of the LAC Booster Stations Rehabilitation and forward to Council for approval.

Utilities Manager's Recommendation

The Utilities Manager recommends that the Board approve the motion as presented.

Body

The project consists of rehabilitation improvements to the Otowi 2 and S-Site booster water production facilities. Improvements include repair or replacement of the existing roofing systems, replacement of exterior doors and windows, and repair and painting of affected interior and exterior building surfaces. Additional work includes improvements to site drainage, repairs to areas with existing water damage, and replacement of roof exhaust fans where required. These improvements are intended to address deterioration and weather-related damage and restore the facilities to good overall condition.

Alternatives

If the Board does not award the project, staff will continue to allocate staff resources to maintenance to mitigate further degradation of the station and pursue a less desirable means to keep the stations operational. 

Fiscal and Staff Impact

Funds were budgeted in FY26 and will be carried over to FY27 to fund the project, no staff will be impacted