File #: AGR1115-25a    Version: 1
Type: General Services Agreement Status: Consent
File created: 3/21/2025 In control: Board of Public Utilities
On agenda: 4/16/2025 Final action:
Title: Approval of the Expenditure and Issuance of a Purchase Order for Services Agreement No. AGR 25-925 with Andritz Hydro for the Purpose of Repairs to the Abiquiu Hydroelectric Plant Draft Tube
Presenters: James Alarid
Indexes (Council Goals): Quality Excellence - Infrastructure Asset Management, DPU FY26 - 2.0 Achieve and Maintain Excellence in Financial Performance
Attachments: 1. A - Andritz Proposal_Abiquiu_20250401, 2. B - Andritz Hydro Terms & Conditions

Title

Approval of the Expenditure and Issuance of a Purchase Order for Services Agreement No. AGR 25-925 with Andritz Hydro for the Purpose of Repairs to the Abiquiu Hydroelectric Plant Draft Tube

Recommended Action

I move that the Board of Public Utilities recommend the Expenditure and Issuance of a Purchase Order for Services Agreement No. AGR 25-925 with Andritz Hydro, for the purpose of repairing the Draft Tube Elbow and Engineering and Supplying the Air Admission Piping in the amount of $538,500.00 and a contingency in the amount of $61,500.00, for a total of $600,000.00, plus Applicable Gross Receipts Tax and forward to Council for approval.

Utilities Manager's Recommendation

The Utilities Manager recommends that the Board approve the motion as presented and forward to Council for approval.

Body

The existing draft tube on unit #3 in Abiquiu has been experiencing wear from cavitation created by the dissolved oxygen injection system. The injection system forces air into the discharge water to enhance the oxygen content of the plant discharge to sustain aquatic life.  The injection piping obstructs the discharge flow and creates cavitation that has worn through steel draft tube. These funds will be applied to repair the damaged section of the draft tube and install a new aeration intake system.  

Alternatives

If the Board does not recommend the expenditure and issuance of a purchase order with Andritz Hydro, staff will not be able to repair the draft tube and will be unable to run this Hydro generator to produce electricity.

Fiscal and Staff Impact

The project has been budgeted through Electric Production in FY 2025 in the amount of $600,000.00.  There are no additional staff impacts to perform the project.