Title
Business Planning for Foxtail Flats
Recommended Action
This presentation is informational only. No formal action is to be taken by the Board of Public Utilities.
Utilities Manager's Recommendation
Recommend that Department of Public Utilities Electric Production staff continue managing Foxtail Flats development, schedule and risk, seek 5-year solar sales agreements and pursue long duration storage.
Body
The Foxtail Flats solar and storage projects are underway. When Foxtail Flats power and energy deliveries are at full capacity in 2027 there will be more capacity than needed to meet the Los Alamos Power Pool's load. The Electric Production division is evaluating several options for managing the excess capacity, considering costs, risks and resilience. This presentation provides current status on this evaluation.
Alternatives
None.
Fiscal and Staff Impact
Attachments
A - Business Planning for Foxtail Flats