Title: Award of Task Order No. 10, Agreement No. AGR24-39a for the Purpose of Determining Relay Settings for the New Transformer in White Rock Substation with Transmission & Distribution Services, LLC in the Amount of $157,262, plus Applicable Gross Receipts Tax for the Term of 180 Days and Approval of Budget Revision 2027-03
Presenters: Dennis Astley; Philo Shelton
Indexes (Council Goals): Quality Excellence - Effective, Efficient, and Reliable Services, Quality Excellence - Infrastructure Asset Management, DPU FY26 - 1.0 Provide Safe and Reliable Utility Services, DPU FY26 - 2.0 Achieve and Maintain Excellence in Financial Performance
Attachments: 1. A - Budget Revision 2027-03 WR Substation T1, 2. B - Task Order No. 10
Related files: 21896-26a

Title

Award of Task Order No. 10, Agreement No. AGR24-39a for the Purpose of Determining Relay Settings for the New Transformer in White Rock Substation with Transmission & Distribution Services, LLC in the Amount of $157,262, plus Applicable Gross Receipts Tax for the Term of 180 Days and Approval of Budget Revision 2027-03

Recommended Action

I move that Council approve Task Order #10, Agreement No. AGR24-39a for the Purpose of Completing the study to connect the White Rock Transformer #1 and connecting the controls with Transmission & Distribution Services, LLC in the Amount of $157,262 plus Applicable Gross Receipts Tax.

 

I further move that Council approve Budget Revision 2027-03 as summarized in Attachment A and that the attachment be made part of the minutes of this meeting.

Utilities Manager's Recommendation

The Utilities Manager recommends that Council approve as presented.

Board, Commission or Committee Recommendation

The Board of Public Utilities reviewed these item at their Regular Meeting on July 22, 2026 and recommends that Council approve as presented.

Body

This is Task Order No.10 with Transmission & Distribution Services, LLC to determine relay settings for the new transformer in White Rock substation and connect the transformer controls to the switchgear building.

Alternatives

We would need to find another outside support service to assist us.

Fiscal and Staff Impact/Planned Item

The Electric Distribution fund balance will be reduced by $169,352 and there are no staff impacts.

Attachments

A - Budget Revision 2027-03 WR Substation T1

B - Task Order No. 10 - T&D