Skip to main content
Logo
File #: 19436-25    Version: 1
Type: Briefing/Report (Dept, BCC) - No action requested Status: Presentations, Proclamations & Recognitions
File created: 11/25/2024 In control: Board of Public Utilities
On agenda: 2/5/2025 Final action: 2/5/2025
Title: Electric Rate Design Proposal
Presenters: Karen Kendall
Indexes (Council Goals): Quality Excellence - Effective, Efficient, and Reliable Services, Quality Governance - Fiscal Stewardship, DPU FY26 - 1.0 Provide Safe and Reliable Utility Services, DPU FY26 - 2.0 Achieve and Maintain Excellence in Financial Performance
Attachments: 1. A - Electric Rate Design Presentation, 2. B - Electric Cost of Service & Rate Study

Title

Electric Rate Design Proposal

Body

Staff has prepared an electric rate design update.  The electric rate design closely follows the recommendations provided in the May 1, 2024 Electric Cost of Service Rate Study prepared by GDS Associates, Inc.  Please keep in mind that DPU is still in budget development and the rate design proposal is subject to change.  The update includes the following:

 

1. FY2024 Electric Distribution financial results and updated projections;

2. Preliminary FY2026 and FY2027 rate recommendations;

3. Status of Time of Use software solution; and

4. Potential Time of Use and Residential Demand rate design. 

 

The update also includes a timeline for the next rate increase:

 

March 19, 2025                     BPU Introduce Ordinance

April 16, 2025                     BPU Ordinance Consideration

May 6, 2025                                          Council Ordinance Introduction

June 10, 2025                      Council Ordinance Hearing

July 1, 2025                                          Electric Rate Effective Date

Attachments

A - Electric Rate Design Presentation

B - Electric Cost of Service & Rate Study