Title
Award of Bid No. IFB26-58 for the Purpose of LASS Cured in Place Piping with AUI, Inc. in the Amount of $849,570, plus Applicable Gross Receipts Tax for the Term of 180 Days.
Recommended Action
I move that the Board of Public Utilities approve the Award of Bid No. IFB 26-58 for the Purpose of Cured in Place Piping with AUI, Inc. in the Amount of $849,570 and a contingency in the amount of $169,914, for a total of $1,019,484, plus Applicable Gross Receipts Tax and forward to Council for approval.
I further move that the Board of Public Utilities approve Budget Revision 2027-02 in the amount of $1,019,484 and forward to Council for approval
Utilities Manager's Recommendation
The Utilities Manager recommends that the Board approve as presented
Body
Cured in Place Piping IFB 26-58 is to clean six conduits, each about 1,300 feet in length and then clean/seal the manhole in the bottom of the canyon. The conduits go from East Jemez Road to a manhole behind the medical center helipad. The cleaned conduits will be lined with a fiberglass reinforced resin to encapsulate the asbestos containing conduit.
Alternatives
DPU will require someone to clean the conduit of debris that has collected in there over the years and plugged the conduit. DPU would then have crews work with the existing Conduit and wear Personal Protective Equipment. This is not recommended because the asbestos conduits will not be encapsulated.
Fiscal and Staff Impact/Planned Item
Budget revision required to carry over $1,019,484 from the previous fiscal year.
Attachments
A - Bid Form - East Jemez CIPP Project
B - Budget Revision 2027-02 LASS