File #: AGR0495-17    Version: 1
Type: General Services Agreement Status: Consent
File created: 3/8/2017 In control: County Council - Regular Session
On agenda: 4/4/2017 Final action:
Title: Award of Bid No. 17-029 in the Amount of $1,374,150.55 plus Applicable Gross Receipts Tax to Star Paving Company for Construction of the North Mesa Phase 1 Improvements Project; Establish a Project Budget in the Amount of $1,683,946 for Roadway Improvements; and Approve Related Budget Revision 2017-20 in the Amount of $100,000.
Presenters: Philo Shelton; Eric Martinez
Indexes (Council Goals): 2018 Council Goal – Quality of Life – Mobility – Maintain and Improve Transportation and Mobility
Attachments: 1. A - Project Budget Spreadsheet.pdf, 2. B - Budget Revision - Form 2017-20.pdf
Title
Award of Bid No. 17-029 in the Amount of $1,374,150.55 plus Applicable Gross Receipts Tax to Star Paving Company for Construction of the North Mesa Phase 1 Improvements Project; Establish a Project Budget in the Amount of $1,683,946 for Roadway Improvements; and Approve Related Budget Revision 2017-20 in the Amount of $100,000.
Recommended Motion
I move that Council award Bid No. 17-029 in the Amount of $1,374,150.55 plus Applicable Gross Receipts Tax to Star Paving Company for Construction of the North Mesa Phase 1 Improvements Project; Establish a Project Budget in the Amount of $1,683,946 for Roadway Improvements; and Approve Related Budget Revision 2017-20 in the Amount of $100,000.
Manager's Recommendation
The County Manager recommends that Council approve the motion as presented.
Body
On March 7, 2017, the County advertised a formal competitive solicitation for project construction through Invitation for Bid No. 17-029. Five responses were received on March 22, 2017, and the evaluation committee is recommending award to Star Paving Company.
This first project phase consists of road reconstruction within the Cumbres del Sol Subdivision, more specifically, Camino Uva and Camino Durasnilla. Road improvements include new asphalt road surfacing and replacement of concrete curb, gutter, valley gutters, drive pads, curb ramps, and sidewalks (in isolated locations). Also included in the work is the replacement of storm drain infrastructure, placement of new signs, pavement markings, and streetlight conduit and pull boxes.
A public meeting was held in conjunction with the regular Transportation Board monthly meeting on February 2, 2017 to obtain input early in the design.
Upon Council approval, the Notice of Award will be sent to the contractor on April 5, 2017 and work will begin on or before May 1, 2017. This contract includes milestone dates and liquidated damages for late completion. All work associated with this contract must be completed by ...