File #: 13618-20    Version: 1
Type: Construction Contract Status: Consent
File created: 11/30/2020 In control: County Council - Regular Session
On agenda: 1/5/2021 Final action:
Title: Award of Bid No. IFB 21-25 for the Purpose of Pajarito Road 16 Inch Transmission Waterline Rehabilitation with AUI, Inc. in the Amount of $688,485, plus Applicable Gross Receipts Tax.
Presenters: James Alarid
Indexes (Council Goals): * 2020 Council Goal - Investing in Infrastructure
Attachments: 1. A - Vicinity Map
Title

Award of Bid No. IFB 21-25 for the Purpose of Pajarito Road 16 Inch Transmission Waterline Rehabilitation with AUI, Inc. in the Amount of $688,485, plus Applicable Gross Receipts Tax.

Recommended Action

I move that Council approve the Award of Bid No. 21-25 for the Purpose of Pajarito Road 16 Inch Transmission Waterline Rehabilitation with AUI, Inc. in the Amount of $688,485, and a 10% contingency in the amount of $68,849, for a total of $757,334, plus Applicable Gross Receipts Tax.

Utilities Manager Recommendation

The Utilities Manager recommends that Council approve as presented.

Board, Commission or Committee Recommendation

The Board of Public Utilities recommends that Council approve as presented.

Body

The initially programmed project involved a reroute of the Pajarito water production transmission line in association with Los Alamos National Laboratory ( LANL) planned parking structure.  However, LANL's parking structure did not receive funding.  Instead, staff choose a different segment water transmission line along Pajarito Road to rehabilitate.  This segment of waterline has experienced 5 leaks over the last six years, and on two occasions damaged nearby facilities and buildings.  This 2,400 linear foot segment of waterline is twice as long as programmed and it will need to use the full amount of the FY2019 profit transfer budget.  The scope of the project is to refurbish an existing concrete cylinder water transmission line located at LANL in the vicinity of Diamond Drive and Pajarito Road.  Attached is a vicinity map showing the location. This line is the primary water supply conveying water from three existing County wells to Pajarito Tanks 4 and 4A which provide domestic and fire service to LANL.  The line will be rehabilitated by installing a structural liner in a 2,400 foot length of the pipeline.  This trenchless method of rehabilitation was chosen due to the difficulties of replacing the line using conventional open ...